Library building construction is underway. Key building project progress points from The Boldt Company include:
- Completed concrete pours at children’s terrace, north stairs and loading dock ramp.
- Installed metal panel on west and northwest sides.
- Installed windows on north side.
- Installed door frames.
- Installed west skylight.
- Installed ductwork on ground level east side.
- Set connecting stair.
- Installed geothermal header
- Installed sewer piping for new storm trap.
- Began installing new double trap storm water tank.
- Began framing at community meeting room.
- Began installation of ceiling grid.
- Continued painting throughout the building.
- Continued masonry work.
- Continued mechanical, electrical and plumbing installations.
Opening day for the new library is on track for early 2025.