Library Building Project Update – August 2024

Library building construction is underway. Key building project progress points from The Boldt Company include:

  • Completed concrete pours at children’s terrace, north stairs and loading dock ramp.
  • Installed metal panel on west and northwest sides.
  • Installed windows on north side.
  • Installed door frames.
  • Installed west skylight.
  • Installed ductwork on ground level east side.
  • Set connecting stair.
  • Installed geothermal header
  • Installed sewer piping for new storm trap.
  • Began installing new double trap storm water tank.
  • Began framing at community meeting room.
  • Began installation of ceiling grid.
  • Continued painting throughout the building.
  • Continued masonry work.
  • Continued mechanical, electrical and plumbing installations.

Opening day for the new library is on track for early 2025.